Renewal of Enzisweiler transport station

The renovation of the Enzisweiler transport station included the replacement of the platforms. Due to the geological conditions, a deep foundation was required. This was carried out in the form of a special proposal instead of the originally planned bored piles with micropiles. The special proposal minimised the impact on the environment and shortened the construction time.
A total of 368 micropiles with a total length of 3140 linear metres were installed for the deep foundations of the platform.
The cable crossing under the track was constructed using the pressing method. A cofferdam construction with 238m² of sheet piling and 75 linear metres of threaded tie rods was used to create the start and finish pits.

Planning services:

Approval planning LPH4 – Shoring and foundation
Implementation planning LPH5 – Shoring and foundations

Info

Client:

DB Station & Service AG

Rosenheim station management

Südtiroler Pl. 1

83022 Rosenheim

Realisation:

Franz Kassecker GmbH

Egerer Street 36

95652 Waldsassen

Execution period:

Spring/Summer 2024

Project details:

238m² sheet pile wall

4 tie rods with a total length of 75m

368 micropiles with a total length of 3140 m’