Bad Lauchstädt Energy Park
Shoring work was required for the construction of a new extinguishing water tank and rainwater retention basin on the site of the planned Bad Lauchstädt energy park. The shoring was designed as a partially back-anchored, closed and sealed sheet pile wall box. These were temporary construction pit stabilisation measures. The excavation pits were realised with 1490 square metres of closed, sealed sheet piling. 45 prestressed grouted piles with a total length of 540 metres were installed to tie back the sheet pile wall.
Planning services:
- Approval planning LPH4 – Shoring and foundation
- Implementation planning LPH5 – Shoring and foundations
Info
Client:
Elektrolyse Mitteldeutschland GmbH
Holzstraße 6
40221 Düsseldorf
Execution:
Franz Kassecker GmbH
Egerer street 36
96652 Waldsassen
Execution period:
Spring 2024
Project details:
1490m² sealed, closed sheet pile wall box
45 prestressed grouted piles with a total length of 540 m’ for back anchoring